Ravenna Members and Residents,
We are pleased to announce that the Ravenna Phase II Water Connection with Roxborough Water and Sanitation District is the final phase for completion of renewal potable water to Ravenna. This is the culmination to the bond financing completed in late 2017 paving the way for this project. Below you'll find a summary of the construction and schedule.
CONSTRUCTION
Construction will be occurring at four (4) sites within the Ravenna Metro District and Roxborough Park Foundation; these sites are described as follows:
SITE 1: Transmission Main (Cicero Court to Roxborough Drive North)
- Connects the 8” water line in Cicero Court to the existing Water Storage Tank adjacent and east of the intersection of Roxborough Drive North and Hermitage Run. A new fire hydrant will be installed.
- All homes on Cicero Court will be fully accessible, except 7790 Cicero Court and 7820 Cicero Court may experience occasional access restrictions.
- A Staging Area will be constructed just north of the Water Storage Tank Site.
- Water line will be installed by horizontal direction drilling (HDD); meaning trenches will only be excavated at each end or bend of the water line and at necessary connections.
- All water services on Cicero Court will experience two to four, 4 to 8 hour water service disruptions. Water service disruptions will be posted 48 hours prior to the service disruption.
- Asphalt and curb and gutter will be removed from the end of Cicero Court.
- Native grasses and golf course sod will be disturbed at this site.
SITE 2: North Connection (Ravenna Entrance and Guard House)
- Connect to existing 12” water main, installation of valve vault and bypass immediately to south of the Ravenna Guard House adjacent and through Dante Drive.
- Open trench methods will be used to place water line.
- Paver roadway will remain intact.
- Water service to Ravenna Guard House, Ravenna Sales Office and Ravenna Golf Course Maintenance Facility will experience one 4 to 8 hour water service disruption. Water service disruptions will be posted 48 hours prior to the service disruption.
- Native grasses and golf course sod will be disturbed at this site.
- Concrete curb and gutter, concrete sidewalk, and asphalt will be disturbed on Dante Drive at southern end of construction area.
- One lane of traffic will remain open at all times and work is to be completed as quickly as possible.
SITE 3: East Connection (Leonardo Place and Fox Paw Trail)
- Connect to existing 8” water line in Leonardo Place with the 8” water line to water line in Fox Paw Trail and a valve vault installation. A fire hydrant will be installed at the end of Leonardo Place.
- All homes on Leonardo Place and Fox Paw Trail will be fully accessible.
- Open trench methods will be used to place water line.
- Water service to all customers on Leonardo Place and to 7250, 7230, 7208, 7188 Raphael Lane will experience one, 4 to 8 hour water service disruptions. Water service disruptions will be posted 48 hours prior to the service disruption.
- All golf cart paths, access to tee boxes, and tee boxes will not be disturbed.
- Native grasses and golf course sod will be disturbed at this site.
- The existing gravel path will be removed and replaced upon completion of work at this site.
- Concrete curb and gutter and asphalt will be removed at this site from both Leonardo Place and Fox Paw Trail.
SITE 4: PRV Relocation (Galileo Way)
- The existing pressure reducing valve in the manhole near the intersection of Palladio Court and Galileo Way will be removed and relocated to the manhole at the intersection of Birolli Place and Galileo Way.
- No water service disruptions are expected during work at this site.
- No asphalt, concrete curb and gutter, sidewalk, native grasses, or golf course sod will be disturbed at this site.
- Full access will remain to Ravenna Golf Course and all homes on Galileo Way, Palladio Court, and Birolli Place.
Upon completion of work at each individual site:
- All native grasses disturbed by work will be reseeded by contractor.
- All asphalt removed will be replaced at full-depth by contractor.
- All concrete sidewalks and curb and gutter removed will be replaced by contractor.
- All golf course sod and landscaping will be replaced by Ravenna Metro District.
Click for larger image
SCHEDULE AND PHASING
November 1 – Work can begin at Site 4, upon completion of work at Site 4 other site work may begin. Work can continue concurrently on Sites 2, 3, 4.
March 1 – All work complete
DISRUPTIONS
- Full access to the neighborhood and golf course will remain with minimal disruptions as noted above
- Construction vehicles and activities will be present on-site.
- Working hours will be between 7 AM and 5 PM Monday through Friday with work not allowed on holidays.
- Dust from construction activities will be kept to a minimum.
If you have any questions, contact Barbara Biggs, General Manager of Roxborough Water & Sanitation District, at 303.979.7286 or [email protected].
Sincerely,
Kevin R. Collins,
Managing Partner